Monday, August 4, 2008

Article, and Opera



Carolyn Younger recently wrote an article for the Napa Valley Register outlining the completion of our reservoir and our upcoming fundraising event "Transforming Lives". The event will be happening on August 17th and will be supporting our new Education and Clean Water fund.

Thanks to everyone who has helped us to get to this point. I am speaking for several thousand of us in saying that we are tremendously grateful.

Friday, July 11, 2008

Downstream Canal Excavation

Though the concrete work on the water gate is completed, there are still a few construction issues remaining for us to take care of over the next few months. Chai began work on the excavation of the downstream canal yesterday and instead of hiring an expensive excavator that would probably sink in the ground once or twice a day, the work will be carried through by local laborers from the community of Balangk. Chai has hired twenty laborers and one foreman to dig the new pathway that will allow the downstream flow to merge with its original stream, O Ta Bet. Hiring manual labor allows us to help employ locals in the villages we work with, providing work opportunities that are hard to come by.

There is also rip-rap and gravel installation work to be done for the water gate wing walls and upstream toe embankment slope. In addition, stop logs still need to be ordered and placed in the water gate. We believe the work will be completed in less than a month’s time.

The first of many Human Translation t-shirts have also been delivered. We are sending most back to the US for our fundraising volunteers, but many of the residents of Balangk who have worked closely with us for the past few years deserve them just as much. Our first recipient was of course Met Sin, the hardworking and talented farmer who lives closest to the reservoir. Below is a picture of Met Sin with the HT shirt posing with Ceda.

Friday, June 20, 2008

Grassing Party

We held our second big grassing party on Thursday, June 19th, to try and complete the embankment grassing for the reservoir. We had around 140 villagers participate along with 70 monks from the Wat Trach pagoda to complete another 20% of the embankment, which means we only have another 15% left. The day would not have been possible without the help of volunteer cooks from Prom Kod village, who cooked all of us a delicious meal, and various other villagers who helped set up the tents, collect firewood, wash dishes, donate ox-carts and refill the water supply. Without the support of the community we wouldn’t be able to pull off these events and therefore appreciate the time and effort that everyone contributes to the project. The monks from Wat Trach also deserve applause as their strength and continued support of the project sets a wonderful example for the community of Balangk to follow. Although we did not finish all the grassing, we still view the day as a huge success because as frustrating as it is working with uncooperative villages, it is more than worth the stress when you see other community members pull together to accomplish the goal at hand.

Thursday, June 5, 2008

Concrete Completion


The concrete work for the water gate is complete as of last Friday, May 30th.
The backfilling of the wing walls was also completed last week allowing us to ride over the bridge of the water gate on our motorbikes. Our contractor's remaining crew is currently working on the rip rap lining while waiting until Sunday to remove the rest of the formwork. Chanda, our contractor and his team are a month and a half ahead of schedule, and we are very excited to see the finished product. We went out on Tuesday to test out the control bars of the gateway, and were very happy to see some red added to the water gate. We are now concentrating our efforts on mobilizing the villages to complete the embankment grassing - just another 30% left! We are organizing another big event on Thursday, June 12th to accomplish the grassing in one day. We believe it will be another success. We still have substantial work to do on the excavation of the downstream canals, and we'll begin our celebrations when that and our Water User Groups are up and running!

Bac Kron and Met Sin (the two living closest to the reservoir) pose on the water gate
Ceda, Tobias, Chai, Bac Kron and Met Sin inspecting the newly painted control bars

Wednesday, May 28, 2008

Monsoon Grassing


Monsoon Grassing Video Montage from Tobias.

Monday, May 26, 2008

Grassing Kickoff

Sunday May 18th, 2008 [Click the photo above for Gallery Shots]

This is a picture taken from last Sunday’s Grassing Kickoff. In order to involve the community on a large scale we decided to put on an event that would allow the villagers to get together for a day of fun and grassing. Along with our partner NGO, Human Resources and Natural Development (HRND), we invited the monks from the local pagoda, Wat Trach, to bless the reservoir and lead the community in the grassing work. It was a frenetic day as 350-400 villagers and monks showed up to help cook, set-up and most importantly, grass the 13, 200 square meter embankment. Although we were only able to grass 50% of the whole embankment, the event was a success as everyone had a great time grassing to the music blaring out of the speakers and slipping on the wet grass after the downpours of the day.

Our focus now is to keep the enthusiasm going among the village chiefs to mobilize their villages in order to finish grassing the rest of the embankment before the monsoon hits. We are depending on the continued participation of the community to complete this part of the reservoir reconstruction project as we are on a critical time schedule. But mobilizing a community of ten villages is a difficult task. It has and will take longer than we thought, but it will be done.

Sunday, May 18, 2008

Video Footage, Apr 11


HV20 Test: Children on Embankment from Tobias on Vimeo.